The Panama Canal Authority (ACP) estimates the investment in the container terminals of Corozal and Telfers, one on the Pacific and one on the Atlantic, at B/.2,600 million, and their added transshipment capacity at 5.0 to 6.0 million TEU (20-foot containers) a year, according to its press release of 9 July 2026. On 7 October 2026, 90 days after the close of document submission on 9 July (own calculation), its press releases did not state the list of prequalified companies or the area and value of the terminals’ land. For a model of Panama logistics real estate, what had been published by then gave an estimated investment and capacity, but not the land area, its value or the start date of works.
What the ACP announced between October 2025 and January 2026
Between 27 October 2025 and 30 January 2026 the ACP gathered the port industry, published the prequalification document and gave estimated project figures: B/.2,600 million (balboas, at par with the dollar) across both terminals and, according to the January press release, added capacity of 5.0 to 6.0 million TEU a year.
The first meeting, on 27 October 2025, was a working meeting by invitation only with port operators and shipping lines. Its press release foresees a market and feasibility study, a general project plan and concessionaire selection, with prequalification and dialogue with the prequalified companies, and places the close of the selection “during the fourth quarter of 2026”. It also states that port capacity in the interoceanic area “is at its operating limit” and puts the increase at 5.0 million TEU a year.
On 30 January 2026 the ACP published the documents for the terminals and for an energy corridor, which is a separate initiative. The Board of Directors also authorised a purchase of real estate from the Nation, through the Ministry of Economy and Finance, for “areas needed for initiatives linked to strengthening the intermodal logistics hub”; the press release gives neither area nor price and does not link those areas to Corozal and Telfers.
Three amendments and the close of submission at Corozal and Telfers
Between 30 March and 9 July 2026 the ACP issued three amendments to the prequalification document and closed document submission on Thursday 9 July, ten days after the 29 June set by amendment No. 2 (own calculation). The press releases give deadlines for amendments No. 1 and 2 and none for No. 3.
| Document | Press release | Clarifications until | Document submission until |
|---|---|---|---|
| Amendment No. 1 | 30 March 2026 (shared with the energy corridor) | 8 April 2026 | 8 June 2026 |
| Amendment No. 2 | 30 May 2026 (the one for amendment No. 3 dates it 29 May) | 8 June 2026 | 29 June 2026 |
| Amendment No. 3 | 5 June 2026 | — | — |
| Close of submission | 9 July 2026 | — | Closed on 9 July 2026 |
The 30 March press release covers both the terminals’ document and the energy corridor’s and does not number the amendment; the press releases of 30 May and 5 June identify it as amendment No. 1.
Amendment No. 2 changed the document review mechanism, specified how consortia are formed, adjusted the documentation of persons linked to the bidder’s corporate structure, updated the guarantees and added annexes on transparency, compliance and conflicts of interest. The press releases for amendments No. 1 and No. 3 do not detail changes of content: the one for No. 3 refers to the Authority’s concessions portal, where its text is.
The dates in this section come from the press releases, not from the texts of the prequalification document and the amendments. None of the press releases of 27 October 2025, 30 January, 30 March, 30 May, 5 June and 9 July 2026 says which document set 9 July as the last day for submission.
What is on record and what is not as of 7 October 2026
As of 7 October 2026 ACP press releases record the estimated investment, the capacity range, the approximate length of construction and the close of submission. Up to that date no press release states the list of prequalified companies, the number of companies that submitted documents, the area and value of the terminals’ land, or the start date of works.
| Item | ACP document | Status as of 7 October 2026 |
|---|---|---|
| Estimated investment in both terminals | B/.2,600 million, press releases of 27 October 2025 and 9 July 2026 | Published |
| Added transshipment capacity | 5.0 M TEU a year (27 October 2025); 5.0 to 6.0 million (30 January and 9 July 2026) | Published, in two wordings |
| Length of construction | “Approximately three years”, press release of 9 July 2026 | Published; no start date for works |
| Number of companies that submitted documents | Press release of 9 July 2026 | — |
| List of prequalified companies | Foreseen in the press release of 9 July 2026 | No release in the ACP news list |
| Area and value of the terminals’ land | No press release | — |
| Real estate purchase from the Nation | Board authorisation, press release of 30 January 2026 | The press release gives neither area nor price nor a link to Corozal and Telfers |
| Close of concessionaire selection | Fourth quarter of 2026, press release of 27 October 2025 | No later date in the press releases |
On 7 October 2026 the Authority’s news list included no release on the list of prequalified companies.
Investment per TEU of annual capacity, between B/.433 and B/.520
According to the ACP press release of 9 July 2026, the estimated investment is B/.2,600 million and the added capacity 5 to 6 million TEU a year. That gives an investment of B/.433 to B/.520 per TEU of annual capacity (2,600 million divided by 6.0 and by 5.0 million; own calculation).
The press releases cited do not say what the investment includes, nor the area and value of the terminals’ land, so they do not allow a value per m² of land to be calculated, only an investment per capacity.
What the press releases leave open after the close of submission
The press releases cited do not say when or through which channel the Panama Canal Authority will publish the list of prequalified companies: the 9 July 2026 one makes it conditional on the end of the evaluation, with no deadline or channel. The only calendar reference for concessionaire selection is the fourth quarter of 2026, given on 27 October 2025.
Prequalification is a prior stage: after it, the October 2025 press release foresees interaction and dialogue with the prequalified companies and then selection. At Corozal Oeste, the ACP reported on 3 March 2017 that it had received no proposals from the prequalified companies and declared the container port tender void, a process distinct from the one for the two terminals.
When will the ACP publish the list of prequalified companies for Corozal and Telfers? As of 7 October no press release set it.